Butt Joint Fusion Method

WELD-IN SADDLE TECHNIQUE

Branches can easily be made by weld-in saddles, even at a later stage of installation. By using weld-in saddles you save material and time. Whereas in case of tees three joints have to be welded, installation of saddle is restricted to mounting the saddle and branch pipe only.

Steps Follows
  • Drill the pipe
  • Warm up the saddle
  • Pipe well and outside pipe
  • Connect the elements
Drill the pipe
Warm up the saddle
Pipe well and outside pipe

ADVANCED BUTT WELDING TECHNOLOGY

KPT is having advanced US and Italian made machines to perform butt welding procedures on PPR pipes of sizes above 110MM. Internationally butt jointing is the most suitable and acceptable procedure for sizes like 160MM, 200MM, 250MM and beyond to adhere to the best quality and durable international standards.

cut the pipe
PPR Pipe Manufacturers
PPR-c
butt welding
Recommended Time For PPR Systems Butt Joints Recommended Time For PPR Systems